How does prefab construction work? From drawing to handover

"Prefab" simply means: made in advance. The walls, floors and roof elements of your home are produced millimetre-precise in our factory in Latvia — including insulation and, if you wish, windows (fitted in the factory or on site, depending on the project). On your building plot we put everything together like a large puzzle. Below is the whole process, step by step.

The lead times at a glance

PhaseLead time
Design, engineering & production drawingsplanned project by project — up to about 3 months for a smaller house, in parallel with your permit and foundation
Material procurement + production in the factoryplanned project by project (CLT about 2 months lead time, windows 2–3 months; panel production itself a few weeks)
Transport to the Netherlands2–5 days
Assembly on sitetypically 3–5 days per storey
Totalwe deliberately do not quote a total in months — the production lead time is confirmed by our project manager with the detailed quotation

Interior finishing comes on top of that — usually 2–4 months, depending on your choices.

What do you arrange yourself before delivery?

  • Building permit in order
  • Foundation prepared and poured — the foundation falls outside the ZTC delivery; we give you millimetre-precise specifications for what our panels require
  • Site accessible for a lorry up to 18 metres and a crane up to roughly 30 tonnes
  • Utility connections ready or in preparation
  • Scaffolding arranged if your home has more than one storey

You receive a checklist from us with dates, so everything is ready on time.

Who assembles your house?

Our own assembly crew from Latvia — no subcontractors, no strangers. The same people who erect our projects in Norway, Sweden and Switzerland. The project leader speaks Dutch or English.

What do you receive at handover?

As-built drawings, CE certification, the warranty certificate and the results of the airtightness test (the so-called blower-door test — a measurement that proves how airtight your home really is). With that you have all the documentation for your municipality, mortgage lender and insurer in hand.